The three-year update

Between full studies, Utah asks the board to look at the last one again at least every three years, and to update it where the numbers have moved.

Get a quote

What the statute says

The same subsection that sets the six-year rule adds a second duty: the board must "review and, if necessary, update a previously conducted reserve analysis no less frequently than every three years". The condominium statute uses the same words. So the shortest compliant rhythm is a full analysis in year 0, a review in year 3, a full analysis in year 6, and so on.

57-8a-211(2); 57-8-7.5(2).

Review or update: the difference

A review means someone compares the analysis with what has actually happened: which projects were done, what they cost, what the reserve balance is now, and whether prices have moved. If everything still holds, the review can conclude that no update is needed, and the board should minute that conclusion.

More often something has changed. Contractor bids rarely match a three-year-old estimate, and a roof that looked fine in year 0 may have aged faster. Then the board updates the analysis: new cost estimates, new remaining lives, a new contribution and funding plan.

Two kinds of update

The Community Associations Institute's reserve study standards describe two update levels, and most Utah firms quote both:

  • Update with a site visit. A specialist walks the property again, checks the condition of each component and revises the numbers. Firms typically price this at roughly 50 to 80 percent of a full analysis fee.
  • Update without a site visit. A desk update using the board's records of completed work and current balances. Fees are often under $1,000.

A common pattern is to alternate: a desk update in year 3, a full analysis with a visit in year 6. If a major component failed early or a big project came in well over budget, a visit is worth paying for.

Update levels: CAI reserve study standards.

What owners see after an update

The association must give owners a summary of "the most recent reserve analysis or update" every year. Once an update is done, that becomes the document the summary is drawn from, and the one an owner receives on request. Chapter five covers how boards usually present it.

Owner summary: 57-8a-211(5).

Questions boards ask

Is a three-year update mandatory in Utah?

A review is. The statute requires the board to review the analysis at least every three years and to update it if necessary. If the review finds nothing has changed, a full update is not required, but record that decision in the minutes.

Can the board do the review itself?

Yes. The statute lets the board conduct the analysis itself or engage a reliable person or organization, and the same applies to reviewing it.

How much does an update cost compared with a full analysis?

Firms often price an update with a site visit at roughly 50 to 80 percent of a full analysis fee, and a desk update at often under $1,000. See the fee guide for full analysis ranges.

Get a quote

It takes three short steps: the ZIP code, your contact details, then a few optional taps.

We are an introduction service, not a reserve study firm. We choose one firm that prepares reserve studies where your community is, tell you who it is, and forward your request only when you agree.

Step 1 of 3

Where is the association?
Get a quote